Date | Comment |
04/30/2023 | The following path has been terminated since there are no active antennas: path 4, location 1, ASHLAND, VA |
04/30/2023 | Callsign WRAF668: The following antenna has been terminated since there are no active frequencies: antenna 4, path 4, location 1, ASHLAND, VA |
04/30/2023 | Callsign WRAF668: The following frequency has been terminated for failure to meet the buildout requirement as required by the applicable rules: frequency 6137.92500000, path 4 |
02/22/2023 | WRAF668, Path 4 Frequency 6137.92500000 has entered the auto termination process on 02/22/2023. |
10/11/2020 | Callsign WRAF668: The following antenna has been terminated since there are no active frequencies: antenna 2, path 2, location 1, ASHLAND, VA |
10/11/2020 | The following path has been terminated since there are no active antennas: path 1, location 1, ASHLAND, VA |
10/11/2020 | The following path has been terminated since there are no active antennas: path 2, location 1, ASHLAND, VA |
10/11/2020 | Callsign WRAF668: The following antenna has been terminated since there are no active frequencies: antenna 1, path 1, location 1, ASHLAND, VA |
10/11/2020 | Callsign WRAF668: The following frequency has been terminated for failure to meet the buildout requirement as required by the applicable rules: frequency 6137.92500000, path 1 |
10/11/2020 | Callsign WRAF668: The following frequency has been terminated for failure to meet the buildout requirement as required by the applicable rules: frequency 6555.00000000, path 2 |
10/11/2020 | Callsign WRAF668: The following frequency has been terminated for failure to meet the buildout requirement as required by the applicable rules: frequency 6625.00000000, path 2 |
08/08/2020 | WRAF668, Path 2 Frequency 6625.00000000 has entered the auto termination process on 08/05/2020. |
08/08/2020 | WRAF668, Path 2 Frequency 6555.00000000 has entered the auto termination process on 08/05/2020. |
08/08/2020 | WRAF668, Path 1 Frequency 6137.92500000 has entered the auto termination process on 08/05/2020. |
04/15/2020 | Construction deadline(s) extended by 60 days per DA 20-414. |